Working with PMs and the business
Turn "the business wants X" into a clear goal, honest options and a plan you can keep, and say "no, but…" when you need to.
Updated since you finished it. We changed this lesson after you marked it done. Your progress is kept.
What broke
This story is made up, but it happens in many companies. Kavya is a backend engineer at a grocery delivery app. Her PM says: "Customers must be able to reschedule a delivery in the app. The business wants it by 1 March."
Kavya does exactly that. She builds a screen to pick any day and any time slot in the next two weeks. The code is clean and well tested.
In week 2 she finds a problem. The warehouse system can only change orders up to 48 hours before delivery. Fixing that needs work from another team. Kavya does not tell anyone. She hopes to find a workaround.
She does not find one. The launch is three weeks late. When it finally ships, only 3% of customers use it. Most people who called support did not want a new day. They wanted to know where their order was.
Nobody asked why the business wanted the feature. Nobody raised the risk while there was still time to act. Kavya's code was good. The way she worked with her PM was not.
The idea in simple words
A product manager (PM) decides what the team should build and why. Marty Cagan of SVPG says the PM owns two big risks. Value: will customers want it? Viability: does it work for the business, for example sales, legal and money? 1 The designer owns usability. The engineers own feasibility: can we build it with the time, skills and technology we have? 1
So you and your PM are not on opposite sides. You share one goal: a result that matters to customers and the business. Cagan says a PM must ensure "a business outcome", not just that a product gets defined. 2
Your job is to bring what only an engineer knows. What is cheap and what is costly. What could go wrong. Which simpler idea solves the same problem.
The key idea. Never answer a request with only "yes" or "no". Ask what problem it solves. Then offer options, each with a cost, a risk and the value it brings. Let the PM choose with you.
Cagan warns about "feature teams", where engineers only build what others decided. He says you then get only about half of the engineers' value. 3 Product teams are measured by outcomes, not output. 3
How it works
Step through one request, from a vague ask to a plan with check-ins. Use Next and Back, or the ← and → keys.
- The PM brings a request from the business. It names a solution and a date, but not the problem or the goal.
- You ask why, for whom, how many, and how you will measure success. The real goal appears: fewer calls to the support team.
- You offer three options. Each has a cost as a range of weeks and a different amount of value. You do not just say yes or no.
- You and the PM choose option B together. You write down one non-goal and the biggest risk, with a date to check it.
- Every week you share progress and risks. When the risk turns out to be real, you say so at once and cut scope to keep the date.
1. Turn the request into a goal
"The business wants X" usually names a solution. Ask questions until you find the problem behind it:
- Why now? What happens if we do nothing?
- Who asks for this, and how many of them?
- How will we know it worked? Which number should move?
Gergely Orosz lists asking "why" again and again as a trait of product-minded engineers. 8 Write the answers down. A goal like "30% fewer support calls about delivery times" lets you judge every option.
2. Say "no, but…" with options
Rarely say a flat no. Say "not like that, but here is what we can do". Give two or three options, each with a cost, a risk and how much of the goal it reaches.
Shape Up, Basecamp's book on product work, calls the time you are willing to spend the appetite. It says an appetite is "completely different from an estimate". 4 You start from the time the problem is worth, then shape a solution that fits. So ask your PM: "How much is this worth to us? Two weeks or two months?"
3. Give estimates as ranges
Early in a project, nobody knows the real size of the work. Steve McConnell's "Cone of Uncertainty" shows that estimates made at the first idea can be 4 times too high or 4 times too low. 6 The range narrows only as you make decisions, such as writing down what you will not do. 6
So say "4 to 8 weeks", not "6 weeks". Then add what will narrow the range: "After I test the warehouse API on Friday, I can give you 5 to 6 weeks." McConnell advises waiting to commit until the range has narrowed. 6
4. Cut scope, not quality
Here, scope means the list of features in the project. When time is short, you can move the date, add people or cut scope. Shape Up fixes the time and lets scope change. 4 It also says "Variable scope is not about sacrificing quality." 5 Its test for a cut is useful: compare the result with what customers do today, not with a perfect version. 5
Good cuts are parts that few users need, cases you can handle by hand at first, or a second phase after launch.
5. Explain technical debt in business terms
"The code is messy" means little to a PM. Martin Fowler explains technical debt with money words. The messy code is the debt. The extra effort it adds to every change is the interest. Cleaning it up is paying back the principal. 7
His example: a feature takes 4 days on clean code but 6 days on messy code. The cleanup costs 5 days. For one feature it is not worth it. For three similar features, cleaning up first is faster. 7 Messy code that you rarely change can stay as it is. 7 So bring numbers: "Each change here costs about 2 extra days. We plan 6 this quarter."
6. Raise risks early
Share bad news early. It costs more the longer you wait. In week 2, the PM can still cut scope, move the date or warn sales. In week 8, the only choice left is to miss the date.
Use a simple format: what you found, what it could cost, what you are doing next, and when you will know more. Say it the same day, even if you are not sure yet.
7. Take part in discovery
Product discovery is the work of finding out what to build before you build it. Join it. Talk to users and read support tickets. Attend the meetings where ideas are judged. Feasibility is your risk. 1 If you join early, you can raise a feasibility problem before the team commits to a plan.
8. Write for people who are not engineers
When you write to the PM, sales or leaders, lead with the decision you need and the date. Then give two or three options in plain words. Put the costs in days, money or customers. Leave out class names and database terms. Orosz lists good communication with non-engineers as one of the traits. 8
Trade-offs
| Way to respond | Keeps trust? | Cost | Use it when |
|---|---|---|---|
| Say yes to everything | No Dates are missed and quality drops. | Hidden: overtime, bugs, debt. | Never as a habit. |
| Flat "no" | No People see you as the one who stops work. | The business goal stays unsolved. | Only for unsafe or illegal requests, with a reason. |
| "No, but…" with options and costs | Yes The PM can make a real choice. | An hour or two of thinking. | Most requests that do not fit the time. |
| Fixed date, cut scope | Yes , if cuts are agreed early. | Some features wait for phase 2. | Hard dates, such as a sale or a law. |
| Fixed scope, move the date | Yes , if you say so early. | Others who planned around the date must adjust. | Every part is a must-have, such as a compliance rule. |
| One exact estimate early | No It will likely be wrong. | Lost trust when the date is missed. | Avoid. Give a range and a date to narrow it. |
Simple rule: bring options, costs and risks early. The PM decides the trade-off with you, not after you.
At work: how a senior uses this
- For every new request, ask: "What problem does this solve, and which number should move?"
- Answer big asks with two or three options. Give each one a cost range, the main risk and how much of the goal it reaches.
- Ask your PM for the appetite: "How much time is this worth?" Then design to fit it.
- Write the non-goals into the plan, so the scope does not grow quietly.
- Give estimates as ranges, and say when and how you will narrow them.
- Raise a risk the day you find it, with what you know and what you will check next.
- Keep a short list of technical debt with its "interest": extra days per change. Bring it to planning with numbers.
- After launch, check the number you agreed on. Share the result with your PM, even if it is bad. 8
With AI
What to ask the agent
"Here is a feature request from my PM. List the questions I should ask before I estimate it: the problem, the users, the success metric and the hidden risks."
"Give me three ways to deliver this, from smallest to fullest. For each one, list what is in, what is out, the main risk and a rough size."
"Rewrite this update for a non-technical PM. Lead with the decision I need, keep it under 150 words, and remove all code terms."
What to check yourself
- The options are real. Check each size against your own codebase. An agent does not know your warehouse API is slow.
- The estimate is a range, and you can explain both ends.
- The business goal comes from your PM or real data. The agent may invent a plausible goal.
- The rewrite still says the risk clearly. Plain words must not hide bad news.
- You talked to the PM in person. An agent can draft the message but cannot build the trust.
Check yourself
Your progress is saved only in this browser. Export it to keep it safe.
You have finished 5 lessons. Your progress lives only in this browser. Export a copy so you don’t lose it.
Go deeper
Show 8 sources and related lessons
- Marty Cagan, “The Four Big Risks”, SVPG (2017) (opens in a new tab)
Value, usability, feasibility and business viability risk, and which role owns each one. - Marty Cagan, “Behind Every Great Product”, SVPG (opens in a new tab)
What a strong product manager is accountable for, and why it is more than writing a backlog. - Marty Cagan, “Product vs. Feature Teams”, SVPG (2019) (opens in a new tab)
Output against outcomes, and what is lost when engineers only deliver what others decided. - Ryan Singer, Shape Up, chapter 3: “Set Boundaries” (Basecamp) (opens in a new tab)
Appetite as a time budget, and fixed time with variable scope. - Ryan Singer, Shape Up, chapter 14: “Decide When to Stop” (Basecamp) (opens in a new tab)
Scope hammering, comparing to what customers do today, and why cutting scope is not cutting quality. - Steve McConnell, “Software Development's Cone of Uncertainty”, Construx white paper (2010) (opens in a new tab)
Why early estimates can be off by 4 times in either direction, and when a commitment becomes meaningful. - Martin Fowler, “Technical Debt” (bliki, 2019) (opens in a new tab)
Cruft, principal and interest, with a worked example in days of work. - Gergely Orosz, “The Product-Minded Software Engineer”, The Pragmatic Engineer (2019) (opens in a new tab)
Nine traits of engineers who care about the product, from asking why to following up after launch.
Related: Influence without authority (coming soon) · Estimation and planning under uncertainty · Managing technical debt · Requirements and non-functional needs · Design docs and RFCs · Clear technical writing (coming soon)